Due to the complexity and size of the project, detailed technical drawings were required by our in-house design team. The site also had sophisticated security with CCTV and fire detection through the use of thermal camaras.
Site security was of upmost importance to us. Therefore, during the construction period the area was fenced and guarded by 360 VideoGuard to ensure intruders didn’t access the area and were deterred.
The sites infrastructure had to be upgraded to accept a new 33kV connection through new DNO grid connection dedicated to the project. Furthermore, a new DNO switch room was built adjacent to the site.
We also discovered an old stone wall drain which wasn’t suitable for drainage connection and had to find an alternative connection point.